[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146937,801,1,"单选题","井巷工程开工前的劳力准备内容，要求不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","落实人员和施工队伍",false,{"key":16,"text":17,"correct":14},"B","完成技术交底工作",{"key":19,"text":20,"correct":21},"C","配备好机具及施工用料",true,{"key":23,"text":24,"correct":14},"D","建立现场管理制度","劳动力准备包括劳动力的配备、人员培训和管理，因此答案应为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]