[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146936,801,1,"单选题","矿建工程施工中设计图纸的现场签证工作主要是因为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","图纸错误",false,{"key":16,"text":17,"correct":14},"B","施工单位根据需要提出变更",{"key":19,"text":20,"correct":21},"C","地质条件的不确定性导致的设计变更",true,{"key":23,"text":24,"correct":14},"D","业主调整设计方案导致设计变更","矿井工程施工中最大的不确定性是地质条件的多变，特别是地质勘探精度不够导致的地质条件与设计图纸不相符，这是施工过程中最大的不确定性因素，也是现场签证的主要工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]