[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146934,801,1,"单选题","施工准备工作中的（ ）还要为确定仓库、堆场面积、组织运输准备之用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","劳动力需要量计划",false,{"key":16,"text":17,"correct":14},"B","施工机械需要量计划",{"key":19,"text":20,"correct":21},"C","材料、设备供应计划",true,{"key":23,"text":24,"correct":14},"D","工程进度计划","材料、设备供应计划主要为组织备料、确定仓库、堆场面积、组织运输之用。安装的设备虽然数量相对少，但占用资金额大，如需要存放，则占用的面积一般也较大，且设备检验、验收也需要一定时间，所以也应予以考虑存放仓库。但这和施工机械需要量计划的性质不同。施工机械需要量计划是根据工程进度计划安排的，所以不是确定仓库、堆场面积、组织运输准备之用的直接依据。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]