[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146932":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146932,801,1,"单选题","关于矿业工程施工的图纸准备工作，正确的要求是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","根据地质条件检查图纸是否满足工程施工要求，否则应更换图纸",false,{"key":16,"text":17,"correct":14},"B","掌握施工对工程地质条件的影响",{"key":19,"text":20,"correct":14},"C","检查图纸的完整、齐全性就是检查其套数，缺一套就缺一个工程内容",{"key":22,"text":23,"correct":24},"D","根据图纸标定的坐标确定建筑物位置，并检查其正确性",true,"图纸工作的内容包括确定拟建工程在总平面图上的坐标位置及其正确性；当地质资料与施工条件不符时，要考虑施工方案的合理性，显然不是更换图纸；检查图纸时要考虑地质条件对工程的影响、相应措施是否合理等；图纸的完整性要检查图纸是否缺张缺页，相互之间是否能衔接，设备与基础是否吻合等内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]