[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146930,801,1,"单选题","关于施工总平面布置的原则，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压风机房位置确定后，则提升机房的布置不宜离其过近",false,{"key":16,"text":17,"correct":18},"B","斜井施工中临时提升机布置在永久提升机的前方",true,{"key":20,"text":21,"correct":14},"C","混凝土搅拌站施工任务繁重应设置在变电所附件",{"key":23,"text":24,"correct":14},"D","为避免炸药库安全事故的影响，宜将其布置在广场的空旷处","通常情况下，提升机房与井筒位置关系相对固定，压风机房应该尽可能靠近井筒负荷中心，同时又要考虑其噪音影响，不宜离井口和提升机房太近。斜井提升机的位置与井口位置方向固定，通常布置临时提升机的位置应考虑尽量不影响永久提升机的安装，便于后期转换。混凝土搅拌站与变电所位置不相干，但应考虑混凝土搅拌站的污染对变电所的影响。炸药库投入期间通常是重大危险源，应远离工业广场和居民、村庄布设，并保持一定安全距离。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]