[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146928,801,1,"单选题","矿井建设期间为综合平衡的“四个排队”中，规模、影响、范围最大是（ ）的排队。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","井巷、土建和机电设备安装工程间",true,{"key":16,"text":17,"correct":18},"B","设备间",false,{"key":20,"text":21,"correct":18},"C","年度计划与季度计划",{"key":23,"text":24,"correct":18},"D","多工序间","在矿井建设期间，必须做好“四个排队”和“六个协调”。所谓“四个排队”，即：井巷、土建和机电设备安装工程的总排队；设备排队(包括提出设备到货的具体要求，以及到货日期的可能误差)；年度计划与季度计划排队；多工序间的排队。矿建、土建、安装三类工程涵盖了矿业工程的全部，三类工程施工的平衡和协调是矿井顺利建成的关键。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]