[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146925":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146925,801,1,"单选题","主副井错开施工的时间应根据最优网络图而定，一般为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1～4个星期",false,{"key":16,"text":17,"correct":18},"B","1～4个月",true,{"key":20,"text":21,"correct":14},"C","2～4个月",{"key":23,"text":24,"correct":14},"D","3～6个月","根据我国多年来的建井实践，通常采用主井先开工、副井后开工的顺序。主副井错开施工的时间通常考虑冻结法施工时应错开积极冻结期，普通法施工时应考虑两个井筒的工程量差异，尽量使两个井筒同时到底，同时先开工时间不少于1个月，便于探明地质情况，利于指导后续井筒及井底的开拓。主副井错开施工的时间应根据最优网络图而定，一般为1～4个月。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]