[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146923":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146923,801,1,"单选题","单位工程施工组织设计的工程量计算，具有（ ）的特点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","根据概算指标",false,{"key":16,"text":17,"correct":18},"B","要求比较准确",true,{"key":20,"text":21,"correct":14},"C","依据初步设计",{"key":23,"text":24,"correct":14},"D","依据企业定额指标","单位工程的施工组织设计是实施性的，故工程量计算要求准确，以保证劳动力和资源需要量计算的正确，便于设计合理的施工组织与作业方式。要做到计算准确，单位工程的工程量必须根据施工图纸和合同规定的定额手册或有关定额资料进行计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]