[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146922":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146922,801,1,"单选题","着重于施工方案内容、总工期和投资概算内容的单项工程施工组织设计，应在（ ）编制完成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同签订前完成",false,{"key":16,"text":17,"correct":14},"B","合同签订后完成",{"key":19,"text":20,"correct":21},"C","招投标前完成",true,{"key":23,"text":24,"correct":14},"D","招投标后完成","单项工程(矿井)施工组织设计的编制主要分两个阶段进行。为满足项目审批和以后的招标工作的需要，由建设单位编制单项工程(矿井)施工组织设计，其内容主要是着重于大的施工方案及总工期总投资概算的安排，对建设单位编制的施工组织设计由上级主管部门进行审批，一般在大规模开工前6个月完成。经过招投标后的施工阶段，由已确定的施工单位或由总承包单位再编制详尽的施工组织设计，作为指导施工的依据。因此答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]