[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146918":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146918,801,1,"单选题","一般井筒施工中，含主井改装的提升运输形式存在三个阶段，其顺序合理的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","副井吊桶提升(主井改装)期、主副井未贯通期和主井临时罐笼提升期",false,{"key":16,"text":17,"correct":18},"B","主副井未贯通期、副井吊桶提升(主井改装)期和主井临时罐笼提升期",true,{"key":20,"text":21,"correct":14},"C","主井临时罐笼提升期、主副井未贯通期和副井吊桶提升(主井改装)期",{"key":23,"text":24,"correct":14},"D","主副井未贯通期、主井临时罐笼提升期和副井吊桶提升(主井改装)期","通常情况下，主副井筒到底后应首先进行短路贯通，最新规程规定，未短路贯通时不允许进行井筒提升系统改装。主井改装期间，副井采用吊桶提升，作为人员上下通道，主井改装完成后，主井采用临时罐笼提升，副井进入永久装备。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]