[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146917,801,1,"单选题","风井若在关键线路上，则安排风井（ ）不合理。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","比主、副井提前开工",false,{"key":16,"text":17,"correct":14},"B","略晚于主、副井开工",{"key":19,"text":20,"correct":21},"C","于主、副井完成后开工",true,{"key":23,"text":24,"correct":14},"D","与主、副井同时开工","因为风井若在关键线路上，应在可能的情况下，安排风井尽早施工，若在主、副井完成后再开工显然是不合理的，会严重影响矿井总工期。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]