[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146915":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146915,801,1,"单选题","施工组织设计的优化，最终应体现在（ ）上。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程规模",false,{"key":16,"text":17,"correct":14},"B","施工速度",{"key":19,"text":20,"correct":14},"C","投资费用",{"key":22,"text":23,"correct":24},"D","经济技术指标",true,"施工组织设计优化需要有项目优化和设计优化的基础，而其本身的优化，则表现在项目的技术方案科学合理，而最终体现在项目的经济技术指标上。项目的施工速度或是工期长短，投资费用的高低，或者工程项目最终形成的规模大小，都是一些单方面的指标，偏弃一方面都可能将这些指标提高，但是它可能是不合理或者不科学的，最终的效益会不高，贻害建设单位，也不利于施工单位。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]