[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146911,801,1,"单选题","在矿山工程项目中，决定地面生产系统布局和影响施工设施布局的，主要是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方案",false,{"key":16,"text":17,"correct":14},"B","土建工程",{"key":19,"text":20,"correct":14},"C","大型施工设备",{"key":22,"text":23,"correct":24},"D","地下产生系统",true,"地下产生系统决定了地面生产系统的布局，同样也影响了施工设施的布局。一个矿山工程整体项目还包括有井巷工程、土建工程，以及采矿、选矿设备，甚至大型施工设备的安装工程内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]