[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146901,801,1,"单选题","矿井进行井上下的联系测量，至少应满足( )的要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重复进行两次",false,{"key":16,"text":17,"correct":14},"B","连续进行两次",{"key":19,"text":20,"correct":21},"C","独立进行两次",true,{"key":23,"text":24,"correct":14},"D","两人进行两次","根据联系测量的要求，井筒联系测量必须独立进行两次，并应在数据的互差不超限的条件下，采用加权平均或算术平均值为最终结果。这表示联系测量的要进行两次，两次测量应独立进行，相互间不能有联系，不能存在相互影响的关系，这样，两次测量的关系与是否连续进行、重复进行以及参与人数等条件无关，只要前后重复测量或连续测量不受到前次测量影响的独立测量就可以，因这种重复进行、连续进行或者两人进行可能对测量的独立性有影响，所以，应选择的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]