[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146826,801,1,"单选题","关于井下巷道掘进循环中各连锁工序时间的确定方法，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由统一定额规定",false,{"key":16,"text":17,"correct":14},"B","根据效益高低确定",{"key":19,"text":20,"correct":21},"C","依据定额并有具体测定修正",true,{"key":23,"text":24,"correct":14},"D","取周围地区平均值","掘进循环中的各连锁工序时间的总和，就可以确定掘进循环时间。因此，各连锁工序时间是编制掘进循环，以及整个巷道施工循环的基础。各连锁工序时间应依据颁发的定额标准，它是一个统计标准，代表了国家或者地区水平和要求，但是，各单位、各施工队有不同情况，施工项目也各有区别，因此不能一概而论，应对施工队的具体施工情况进行测定、修正，这样的T序时间才是可靠的，依据这个数据编制的循环图表才是既符合国家产业要求，有实际基础和可执行的。因此，C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]