[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146806":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146806,801,1,"单选题","选择立井机械化施工配套作业线的基本依据是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","井筒的类型",false,{"key":16,"text":17,"correct":14},"B","抓岩机型号",{"key":19,"text":20,"correct":21},"C","井筒直径和立井深度",true,{"key":23,"text":24,"correct":14},"D","井筒支护形式","一般选择立井机械化施工配套作业线主要看立井的深度和井筒直径大小，这两个参数决定了当前机械化配套设备的规模、能力以及工程量，决定设备使用的合理性。例如5m以上井筒就可能布置大型掘砌设备；400m深度的井筒才能有相对较高的机具效率。井筒的类型是指主井、副井或风井，与施工配套关系不大，抓岩机型号只与其他施工设备的配套选择有关，和整套作业线无关；井筒支护形式和井筒施工(尤其是掘进工序)关系不大。故合理的答案是C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]