[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146797":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146797,801,1,"单选题","下列关于地面预注浆堵水的说法中正确的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","含水层距地表较深时，采用地面预注浆较为合适",false,{"key":16,"text":17,"correct":14},"B","地面预注浆的钻注浆孔和注浆工作都可在建井期同时进行",{"key":19,"text":20,"correct":14},"C","钻孔布置在大于井筒掘进直径3～5m的圆周上",{"key":22,"text":23,"correct":24},"D","注浆时，若含水层比较薄，可将含水岩层一次注完全深",true,"地面预注浆的钻注浆孔和注浆工作都是在建井准备期在地面进行的。含水层距地表较浅时，采用地面预注浆较为合适。钻孔布置在大于井筒掘进直径1～3m的圆周上，有时也可以布置在井筒掘进直径范围以内。注浆时，若含水层比较薄，可将含水岩层一次注完全深。若含水层比较厚，则应分段注浆。分段注浆时，每个注浆段的段高应视裂隙发育程度而定，裂隙愈发育段高应愈小，一般在15～30m之间。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]