[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146790":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146790,801,1,"单选题","按矿山建设基本程序，矿井项目最后要完成的工作是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工验收",false,{"key":16,"text":17,"correct":14},"B","交付使用",{"key":19,"text":20,"correct":21},"C","项目后期评估",true,{"key":23,"text":24,"correct":14},"D","生产准备","按照矿山建设的基本程序要求，一个建设项目不是从设计开始，也不是从可行性研究开始，而是从资源勘探开始；而一个建设项目的结束，不是竣工验收，也不是交付使用，更不是生产准备，而是竣工验收若干年后，全面总结项目的决策、实施到经营的各时期中成功或失败的经验教训，完成项目建设的后评估。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]