[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146738,801,1,"单选题","基坑需开挖至地下水位线以下时，降水工作应当延续到( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基坑开挖前",false,{"key":16,"text":17,"correct":14},"B","基坑挖至地下水位线前",{"key":19,"text":20,"correct":21},"C","基础施工完成",true,{"key":23,"text":24,"correct":14},"D","基础土方开挖完毕","基坑(槽)和管沟周围的地面应有可靠的排水措施，杜绝地面水流入坑内，防止因冲刷造成边坡塌方和基土破坏。在地下水位以下挖土，应采取降水、排水措施，将水降至槽底以下500mm，降水工作应持续到基础施工完成。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]