[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146733,801,1,"单选题","按场地平整的施工程序，经过现场勘察、清除地面障碍后，即应进行( )工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计算挖方量",false,{"key":16,"text":17,"correct":14},"B","计算填方量",{"key":19,"text":20,"correct":21},"C","标定",true,{"key":23,"text":24,"correct":14},"D","平整土方","根据场地平整的施工程序，清除场地障碍物以后，在正式施工、进行场地平整前，先应该确定施工范围，就是标定。标定工作包括标定平整范围、设置水准点并测定标高、操平放线。标定后还要建立方格网，然后计算确定挖、填工程量，这以后才能开始平整工作。故C。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]