[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146732,801,1,"单选题","基坑边缘的施工机械应与基坑边缘保持( )m以上距离。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0．3",false,{"key":16,"text":17,"correct":14},"B","0．5",{"key":19,"text":20,"correct":21},"C","1",true,{"key":23,"text":24,"correct":14},"D","2","基坑周边不得超堆荷载，在基坑边缘上侧堆土或材料以及移动施工机械时，应与基坑边缘保持1m以上距离，以保证边坡的稳定。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]