[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146731":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146731,801,1,"单选题","地下连续墙槽段接头时应待混凝土( )后即拔出接头管。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","浇筑完毕",false,{"key":16,"text":17,"correct":18},"B","初凝",true,{"key":20,"text":21,"correct":14},"C","终凝",{"key":23,"text":24,"correct":14},"D","养护结束","接头管应能承受混凝土压力，并避免混凝土在两槽段问串浆。待混凝土初凝(强度达约0．05～0．2MPa)后拔出接头管，形成相邻单元槽段的接头；要避免拔管过早导致混凝土坍落，或过迟出现拔管施工困难的情况。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]