[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146660,801,1,"单选题","立井井筒表土段施工为冻结法施工时，其冻结深度应穿过风化带延深至稳定的基岩（）以上。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","8m",false,{"key":16,"text":17,"correct":18},"B","10m",true,{"key":20,"text":21,"correct":14},"C","15m",{"key":23,"text":24,"correct":14},"D","20m","2020版教材页码P385-388 现行煤矿安全规程规定：采用冻结法开凿立井井筒时冻结深度应穿过风化带延深至稳定的基岩10m以上。基岩段涌水较大时，应加深冻结深度。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]