[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146644,801,1,"单选题","新建矿井在建井期间的矿井水文地质资料经收集、整理、（）后，全部移给交生产单位。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分析",true,{"key":16,"text":17,"correct":18},"B","复印",false,{"key":20,"text":21,"correct":18},"C","人档",{"key":23,"text":24,"correct":18},"D","修改","2020版教材页码P366-368 新建矿井应当按照矿井建设的有关规定，在建井期间收集、整理、分析有关矿井水文地质资料，并在建井完成后将资料全部移交给生产单位。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]