[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146637,801,1,"单选题","工程进度交换图纸的性质，是用于（）的图纸。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","和相邻矿井工程施工单位交换",false,{"key":16,"text":17,"correct":18},"B","提供给上级机关并逐月交换",true,{"key":20,"text":21,"correct":14},"C","与兄弟单位用于经验交流的交换",{"key":23,"text":24,"correct":14},"D","向地方政府主管部门汇报的","2020版教材页码P353-354 工程进度交换图纸：为便于上级部门掌握施工进度和工程情况（包括地质、水文条件的变化，施工方案的重大改变，安全、质量事故等影响正常施工的因素），矿业工程实行工程图纸交换制度。工程图纸交换制度是矿山工程特有的一种技术档案管理制度。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]