[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146570,801,1,"单选题","当对一关键工作延误采取措施时，合理的结论是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","尽早调整紧邻后续关键工序有利于尽早恢复进度正常",true,{"key":16,"text":17,"correct":18},"B","重新安排前续关键工序时间更容易满足原工期要求",false,{"key":20,"text":21,"correct":18},"C","矿建工程一般都可以通过对头掘进的方法恢复工期进度",{"key":23,"text":24,"correct":18},"D","平行作业法对提高不同条件下的井巷施工速度都很有效","2020版教材页码P188-191 当网络计划某一关键工作发生延误时，肯定会对后续工作的正常开始和项目总工期产生影响，因此，必须采取相关措施。首先要分析该关键工作发生延误的原因，并针对原因采取措施，最常用的措施是缩短后续关键工作的持续时间，达到满足工期的要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]