[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146569,801,1,"单选题","通常，工程进度滞后而要求更新的最终目的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","延长工期",false,{"key":16,"text":17,"correct":18},"B","调整后续工程进度计划",true,{"key":20,"text":21,"correct":14},"C","调整前期工程量内容",{"key":23,"text":24,"correct":14},"D","增加索赔机会","2020版教材页码P188-191 工程进度更新主要包括两方面的工作，即分析进度偏差的原因和进行工程进度计划的调整，以满足合同要求。常见的进度拖延情况有：计划失误；合同变更；组织管理不力；技术难题未能攻克；不可抗力事件发生等。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]