[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146568":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146568,801,1,"单选题","确定建井工期的方法，通常是根据（）来确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","累计重要土建、安装工程完成时间",false,{"key":16,"text":17,"correct":18},"B","井巷工程的施工期",true,{"key":20,"text":21,"correct":14},"C","设备的最终到货时间",{"key":23,"text":24,"correct":14},"D","矿建、土建、安装时间总和","2020版教材页码P175-185 矿井建设的工期应当根据矿井建设的关键线路来推算，在具体的推算时，又可以结合工程实施的情况，依据井巷工程的施工期来推算，或依据与井巷工程紧密相连的土建、安装工程施工期来推算，也可依照主要生产设备订货、到货和安装时间来推算。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]