[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146566,801,1,"单选题","矿业工程在确定工期过程中，做法不合理的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合理安排土建与安装的综合施工",false,{"key":16,"text":17,"correct":14},"B","要因地制宜，量力而行",{"key":19,"text":20,"correct":14},"C","合理配备所需资源",{"key":22,"text":23,"correct":24},"D","总工期必须大于合同工期",true,"2020版教材页码P173-174 矿业工程项目工期确定时要注意： （1）合理安排土建与安装的综合施工； （2）因地制宜，量力而行； （3）配备所需资源； （4）考虑外部条件的配合情况，包括施工所需施工图纸、水、电、气、道路及业主所提供的工程设备、材料到货情况，天气情况，注意冬、雨期等影响。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]