[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146564,801,1,"单选题","采用定额计算法确定工序延续时间，计算参数不包括（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工序的工程量",false,{"key":16,"text":17,"correct":18},"B","工序的辅助时间",true,{"key":20,"text":21,"correct":14},"C","参与该工序的人力或机械数量",{"key":23,"text":24,"correct":14},"D","工序的产量定额","2020版教材页码P175-185 因为工序的辅助时间已经包含在定额之内。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]