[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146563,801,1,"单选题","下面属于施工准备工作中的工程准备的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","图纸会审",false,{"key":16,"text":17,"correct":18},"B","四通一平",true,{"key":20,"text":21,"correct":14},"C","制定施工设备计划",{"key":23,"text":24,"correct":14},"D","选择分包商","2020版教材页码P165-169 图纸会审属于技术准备，制定施工设备计划属于物资准备，选择分包商属于协作协调，工程准备包括现场施测、广场平整、地质补堪、临时设施以及施工用混凝土配合比、新工艺新技术等。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]