[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146561,801,1,"单选题","施工准备工作中的（）还要为确定仓库、堆场面积、组织运输准备之用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","劳动力需要量计划",false,{"key":16,"text":17,"correct":14},"B","施工机械需要量计划",{"key":19,"text":20,"correct":21},"C","材料、设备供应计划",true,{"key":23,"text":24,"correct":14},"D","工程进度计划","2020版教材页码P165-169 材料需要量计划，主要为组织备料，确定仓库、堆场面积、组织运输之用，以满足施工组织计划中各施工过程所需的材料供应量。安装的设备虽然数量相对少，但占用资金额大，如需要存放，则占用的面积一般也较大。在安排供应计划中，除应考虑工程进度外，还应留有足够的设备检查验收的时间，进口设备另要考虑入关、运输等时间余量。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]