[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146557":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146557,801,1,"单选题","建设单位编制的单项工程施工组织设计需要（）组织审批。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位的上级主管部门",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","地方行政主管部门",{"key":23,"text":24,"correct":18},"D","施工单位的上级机关","2020版教材页码P151-152 当前，单项工程（矿井）施工组织设计的编制有两种，一种是为满足招标工作的需要，由建设单位编制单项工程（矿井）施工组织设计，它由上级主管部门进行审批。一种是由施工单位编制，根据用途不同，施工单位编制的施工组织设计也有两种，一种在招投标阶段使用，是施工单位为投标、中标用，也称为一次性组织设计书，它注重说明施工方案、总工期和概算等内容；经过招投标后的施工阶段，由已确定的施工单位或由总承包单位再编制详尽的施工组织设计，作为指导施工的依据。施工单位编制的施工组织设计只需上级单位组织审批，而作为指导施工的施工组织设计，也要经过建设单位同意。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]