[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146556,801,1,"单选题","主副井错开施工的时间应根据最优网络图而定，一般为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1～4个星期",false,{"key":16,"text":17,"correct":18},"B","1～4个月",true,{"key":20,"text":21,"correct":14},"C","2～4个月",{"key":23,"text":24,"correct":14},"D","3～6个月","2020版教材页码P157-162 井巷工程开拓速度的提高，使得主井井筒系统经常接近关键线路，这种平行交叉施工方案只是缩短了井下巷道的开拓时间，而延长了井筒提升系统的建设工期，更加剧了主井提升系统的建设工期矛盾，因此，现在更多企业主张箕斗装载硐室与井筒一起施工。主、副井错开施工的时间应根据最优网络图而定，一般为1-4个月。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]