[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146515,801,1,"单选题","防水混凝土的施工技术要求，说法错误的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地下水位应降至防水工程底板垫层下≥500mm",false,{"key":16,"text":17,"correct":18},"B","为增强混凝土的均匀性，机械搅拌不少于1min",true,{"key":20,"text":21,"correct":14},"C","应在终凝前覆盖浇灌的混凝土，保温养护不少于14d",{"key":23,"text":24,"correct":14},"D",";防水混凝土结构内部设置的各种钢筋或绑扎钢丝不得接触模板","2020版教材页码P48-51 混凝土必须严格按施工配合比配制，为增强混凝土的均匀性，机械搅拌不少于2min。拌制好的混凝土须及时浇筑，分层浇筑时原有混凝土浇筑层不得有初凝现象。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]