[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146483":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146483,801,1,"单选题","立井井筒穿过预测涌水量大于（）的含水岩层或破碎带时，应采用地面或者工作注浆预注浆法进行堵水或加固。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8m3／h",false,{"key":16,"text":17,"correct":14},"B","9m3／h",{"key":19,"text":20,"correct":21},"C","10m3／h",true,{"key":23,"text":24,"correct":14},"D","11m3／h","2020版教材页码P109-110 立井井筒穿过预测涌水量大于10M3／H的含水岩层或破碎带时，应采用地面或者工作注浆预注浆法进行堵水或加固。注浆前，必须编制注浆工程设计和施工组织设计。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]