[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146479":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146479,801,1,"单选题","关于井下巷道掘进循环中各连锁工序时间的确定方法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由统一定额规定",false,{"key":16,"text":17,"correct":14},"B","根据效益高低确定",{"key":19,"text":20,"correct":21},"C","依据定额并有具体测定修正",true,{"key":23,"text":24,"correct":14},"D","取周围地区平均值","2020版教材页码P134-135 掘进循环时间是掘进各连锁工序时间的总和，工序时间应以已颁发的定额为依据，但由于每个掘进队的具体情况不同，因此必须对施工的掘进队进行工时测定。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]