[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146474,801,1,"单选题","关于巷道施工的掘进与永久支护顺序作业方式特点，说法正确的是其（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","要求巷道断面大",false,{"key":16,"text":17,"correct":14},"B","作业人员多",{"key":19,"text":20,"correct":14},"C","施工人员分工明确",{"key":22,"text":23,"correct":24},"D","成巷速度较慢",true,"2020版教材页码P122-125 巷道施工掘进与永久支护顺序作业，是指掘进与支护两大工序在时间上按先后顺序施工，即先将巷道掘进一段距离，然后停止掘进，边拆除临时支架，边进行永久支护工作。这种施工作业方式的特点是掘进和支护轮流进行，由一个施工队来完成，因此要求工人既会掘进，又会支护。该作业方式主要工作单一，需要的劳动力少，施工组织比较简单，与平行作业相比成巷速度较慢。因此，答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]