[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146470,801,1,"单选题","关于钻井法凿井的钻井与井壁施工的先后关系，说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻完后下沉井壁",true,{"key":16,"text":17,"correct":18},"B","钻一段沉一段",false,{"key":20,"text":21,"correct":18},"C","先下沉后钻井",{"key":23,"text":24,"correct":18},"D","与钻头同时跟进","2020版教材页码P108 采用钻井法施工的井筒，其井壁多采用在地面制作的管柱形预制钢筋混凝土井壁。待井筒钻完后，提出钻头，用起重大钩将带底的预制井壁悬浮在井内泥浆中，利用其自重和注入井壁内的水重缓慢下沉。同时，在井口不断接长预制管柱井壁。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]