[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146463,801,1,"单选题","综合机械化施工配套作业线设备配套方案适用于井筒直径（）m、井筒深度（）m的大型凿井工程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5-12m；300-600m",false,{"key":16,"text":17,"correct":18},"B","5-12m；400-1000m",true,{"key":20,"text":21,"correct":14},"C","8-15m；300-600m",{"key":23,"text":24,"correct":14},"D","8-15m；400-1000m","2020版教材页码P115-117 综合机械化施工配套作业线设备配套方案适用于井筒直径5-12m、井筒深度400-1000m的大型凿井工程。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]