[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146462":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146462,801,1,"单选题","在立井施工中，（）工作约占整个掘进工作循环时间的50％～60％，是决定立井施工速度的关键工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻眼爆破",false,{"key":16,"text":17,"correct":18},"B","装岩提升",true,{"key":20,"text":21,"correct":14},"C","井筒支护",{"key":23,"text":24,"correct":14},"D","通风与排水","2020版教材页码P110-113 在立井施工中，装岩提升工作是最费工时的工作，它约占整个掘进工作循环时间的50%-60%，是决定立井施工速度的关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]