[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146455":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146455,801,1,"单选题","巷道施工的装载与运输是掘进中劳动量大，占循环时间最长的工序，一般情况下它可占掘进循环时间的（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%-30%",false,{"key":16,"text":17,"correct":14},"B","15%-35%",{"key":19,"text":20,"correct":21},"C","35%-50%",true,{"key":23,"text":24,"correct":14},"D","50%-70%","2020版教材页码P122-125 巷道施工的装载与运输是掘进中劳动量大，占循环时间最长的工序，一般情况下它可占掘进循环时间的35%-50%。选择合理的装运设备，加快掘进装运工作，可有效提高巷道的掘进速度。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]