[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146394":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146394,801,1,"单选题","对于有色金属矿山井筒采用激光指向时，每掘进（）应采用井筒中心线校核。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10-20m",false,{"key":16,"text":17,"correct":14},"B","10-30m",{"key":19,"text":20,"correct":21},"C","20-30m",true,{"key":23,"text":24,"correct":14},"D","20-50m","2020版教材页码P3-6 对于有色金属矿山井筒采用激光指向时，每掘进20-30m应采用井筒中心线校核，其偏差不得大于15mm，砌筑时则应每隔10-20m进行校核，偏差不得大于5mm。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]