[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146393":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146393,801,1,"单选题","贯通测量的技术工作内容和要求,错误的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应保证原始资料的可靠性和起算数据的准确无误",false,{"key":16,"text":17,"correct":14},"B","对于精度要求高的贯通，应有提高精度的相应措施",{"key":19,"text":20,"correct":14},"C","贯通测量导线最后的（不少于3个）测站必须设置牢固",{"key":22,"text":23,"correct":24},"D","最后一次标定贯通方向时，两个相向工作面间的距离不得小于30m",true,"2020版教材页码P3-6 贯通测量导线最后的（不少于3个）测站必须设置牢固。最后一次标定贯通方向时，两个相向工作面间的距离不得小于50m。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]