[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146391":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146391,801,1,"单选题","关于施工测量控制网的布设原则，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","精度不满足新的施工测量控制网要求时，必须另测设施工测量控制网",false,{"key":16,"text":17,"correct":18},"B","局部控制网精度的选取还应考虑施工方法的因素",true,{"key":20,"text":21,"correct":14},"C","矿区的整个施工控制网的精度应均匀一致",{"key":23,"text":24,"correct":14},"D","控制网的测点应根据矿井巷道布置图设计确定","2020版教材页码P1-3 选项A，如精度不能满足时，则可选用已有控制网的个别点作为新建控制网的起算依据。选项C，整个施工控制网的精度并不均匀一致。选项D，控制网的测点，应根据总平面图和施工总布置图设计确定。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]