[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146356,801,1,"单选题","强夯法处理地基的施工特点，说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","使用机具设备较多",false,{"key":16,"text":17,"correct":14},"B","施工工艺复杂",{"key":19,"text":20,"correct":14},"C","费用较高",{"key":22,"text":23,"correct":24},"D","施工速度快",true,"2020版教材页码P67-71 强夯法又称动力固结法，是利用大吨位夯锤起吊到6～30m高度后夯落的作用加固土层的方法。这种方法的特点是设备简单，施工工艺、操作简单；适用土质范围广，加固效果显著；工效高，施工速度快；施工费用低，节省投资。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]