[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146355,801,1,"单选题","对灰土垫层的施工，做法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","灰土垫层的面层宽度应和基础宽度一致",true,{"key":16,"text":17,"correct":18},"B","灰土的颜色要求均匀、一致",false,{"key":20,"text":21,"correct":18},"C","铺垫灰土前基槽内不得有积水",{"key":23,"text":24,"correct":18},"D","灰土应在铺垫当天将其夯实","2020版教材页码P67-71 灰土强度与石灰掺量有关。体积配合比一般采用3:7或2:8（石灰:土），人工搅拌不少于三遍，均匀，颜色一致，并适当控制含水量。垫层厚度应符合设计，保证软弱土层所承受垫层底面的作用小于其承载能力。垫层每边超出建筑物墙基础外缘的宽度不应小于垫层的厚度，且不得小于2m。 施工前基槽应平整、干净，不得有积水，并经试夯确定夯压遍数。灰土应当日铺填夯压，入槽灰土不得隔日夯打。夯筑施工应分段分层进行，分段施工时不得在墙角、柱基及承重窗间墙下接缝，接缝处理应符合要求。夯实后的灰土30d内不得受水浸泡，并应及时进行基础施工与基坑回填，或在表面做临时性覆盖，避免日晒雨淋。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]