[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146352":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146352,801,1,"单选题","基坑土方开挖的顺序和方法的正确原则是“开槽支撑、先撑后挖、（）、严禁超挖”。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一次到底",false,{"key":16,"text":17,"correct":14},"B","分片开挖",{"key":19,"text":20,"correct":21},"C","分层开挖",true,{"key":23,"text":24,"correct":14},"D","先浅后深","2020版教材页码P60-63 基坑土方开挖的顺序、方法必须与设计工况一致，并遵循“开槽支撑、先撑后挖、分层开挖、严禁超挖”的原则。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]