[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146305,801,1,"单选题","可提高混凝土抵抗体积变形的措施有（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","选择品质优良的硅酸盐水泥",false,{"key":16,"text":17,"correct":14},"B","采用速拌、速浇、速搅的措施",{"key":19,"text":20,"correct":14},"C","提前拆模，加快降温速度",{"key":22,"text":23,"correct":24},"D","混凝土体内安设冷却管控制水化热",true,"2020版教材页码P31-37 混凝土的体积变形包括收缩变形、干缩变形、温度变形等内容。控制混凝土的水化升温、延缓降温速率、减小混凝土收缩、提高混凝土的极限拉伸强度、改善约束条件等方面是防止大体积混凝土温度裂缝的主要出发点。常用的控制措施有： （1）合理选择水泥品种和混凝土配合比，尽量选用如矿渣水泥、火山灰水泥等水化热低的水泥，并利用外加剂或外掺料减少水泥的用量。（2）采取分层或分块浇筑，合理设置水平或垂直施工缝；或在适当的位置设置施工后浇带，以放松约束程度。（3）适当延长养护时间和拆模时间，延缓降温速度。（4）在混凝土内部预埋冷却水管，通过循环冷却水，强制降低混凝土水化热温度。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]