[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146292,801,1,"单选题","关于注浆堵水说法不正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当井筒预计穿过较厚裂隙含水层或者裂隙含水层较薄但层数较多时，可采用地面预注浆",false,{"key":16,"text":17,"correct":18},"B","在制定注浆方案后，施工井筒检查孔",true,{"key":20,"text":21,"correct":14},"C","当含水层富水性较弱时，可以采用井筒工作面预注浆",{"key":23,"text":24,"correct":14},"D","注浆终止深度，大于井筒最下部含水层的埋深或超过井筒深度10∽20m","在制定注浆方案前，施工井筒检查孔，以获取含水层的埋深、厚度、岩性及简易水文观测、抽（压）水试验、水质分析等资料。故选B。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]